Thursday, May 9, 2013

The Final Countdown

With less than 10 days to complete the house, we are working day and night to achieve our goal. This past weekend the majority of the exterior was painted, as well as finishing up the siding. The tile in the kitchen was set today and is waiting to be grouted tomorrow. The back porch has stairs and the front porch stairs are in progress. Tuesday, the insulation crew insulated underneath the house. Once the inspector approves the electrical work, we will have permanent power. We expect that within a day or two. With a forecast of rain Friday and Saturday, our goals are to complete the soffit, the stairs, and the painting. The digital fabrication on the canopy has been cut on the plasma cutter and is waiting installation. The sliding door in the living room/kitchen has also started construction. On the interior, the remaining doors are being painted and installed and the trim has been profiled.
Back Porch Stairs

Painting Doors

Trim

Front Porch 

Front Porch Bracket

Canopy 