While the weeks are quickly passing by, the pressure to work countless hours each and every day has been key. With the help of the CenturyLink volunteer group this past weekend, all of the priming and painting has been completed on the interior of the house! We have also been able to finish the front deck and start on the back deck which will allow Mrs. Peggy to enjoy the exterior space that she loves. Yesterday, we began to wire the electrical outlets and hope to get the power turned on by the end of this week which will allow us to stay on site longer into the night in order to accomplish more each day. Since drainage was a big issue on the site, we have completed the french drain which is tied to the ditch by the road. The french drain was tested yesterday with the rain and is working just as we had hoped!
-Hannah Terrell