The second week has been full of progress thus far. Beginning early Monday morning, we started to layout the corners of the house which really gave the project a sense of life seeing how it would really be on the site. We have also got the necessities on the site including the trailer (Davison Trucking) and temporary power pole.
With another early start Wednesday morning, we set out the location of all 26 piers for the foundation of the home by running series of strings to set out the cross points as to where the piers would be placed. We are looking forward to drilling the holes toward the end of this week and staying on track with the schedule. Everything is looking great and we hope to keep the positive momentum going!
-Hannah Terrell-